Tribhuvan International Airport is improving its facilities following development works are in progress.
- Runway, Taxiway, parking, Overlay & extension of equipment yard is Completed being completed
- Bay no 9 completed.
- Radar Antenna overhaul completed.
- Helipad to east is being completed.
- VOR stand by Added.
- 01 large foam tender purchased.
- International sterile zone with a capacity of 450 pax and a new arrival walkway completed.
- Golden Gate maintenance completed.
- 02 X-Ray machines added for security purpose.
- Chairs and trolleys are being added according to the need.
- CUTE is being implemented soon.
- Enclosure outside terminal building completed.
- Press conference room has been shifted to the enclosure.
- Conveyor belt maintenance going on.
- Targetting to NTY 2011 beautification work in progress like floor cleaning, wall Painting & Improvement of electrification.
- Immigration counters to be made friendly and attractive.
- 175 CCTV Camera for whole airport surveillance already completed.
- Domestic A/C parking area to be maintained very soon.
- Car parking outside international terminal golden, gate area EOI Approved.
- New FID system 90% completed.
- Due to Traffic congestion in day time night time operation to be done & govt. will give subsidize to the interested operators.